- Status check: what is confirmed on 7 November 2026
- Why the numbers keep changing
- Does 50,000 Rubin GPUs fit in 120 MW?
- Timeline: from order to rentable capacity
- How Vera Rubin fits with Yotta's Blackwell supply
- Where IndiaAI compute fits
- What Indian GPU buyers should do now
- Worked example: when would Rubin be worth paying more for?
- Questions to put to Yotta, or any Indian GPU cloud, before you sign
- Data residency, DPDP and the tax angle
- How eCorpIT can help
- References
Summary. Yotta Data Services plans to put NVIDIA Vera Rubin GPUs into a new 120 MW data centre, D4, at its Greater Noida campus, with deliveries reported for March to June 2027 and go-live for May to August 2027. That is a plan given in interviews, not a signed order: neither Yotta nor NVIDIA has published a release on it. The GPU count has moved from 50,000 in late August to 40,000 in a 10 September interview. NVIDIA's side is firmer. Vera Rubin began ramping into full production on 31 May 2026 and has been generally available on Oracle Cloud Infrastructure since 27 October. NVIDIA sizes a 100 MW AI factory at 40,000 Rubin GPUs, which puts 50,000 beyond what 120 MW can hold. Yotta's announced pipeline is Blackwell: 20,736 B300 GPUs for its 60 MW D2 site, more than 10,000 of them committed to the IndiaAI Mission. Our verdict: plan 2027 work on capacity you can rent now (Yotta lists B200 bare metal at ₹473 per GPU-hour), treat Indian Vera Rubin as a second-half 2027 option, and sign nothing that depends on it without delivery, substitution and exit clauses.
About this article. For Indian CTOs, AI leads and procurement teams planning GPU capacity for 2027. On 7 November 2026 we checked Yotta's plans against its releases, media page, price list and the CEO interviews cited; NVIDIA's claims against its newsroom, product page and October 2026 datasheet; and the policy points against C-DAC's tender, PIB, PRS and the DPDP Rules (G.S.R. 846(E), 13 November 2025). Business Standard's 27 August interview page refused automated access, so we used a published summary of it. This is not investment, procurement, legal or tax advice, and no vendor paid for inclusion. Researched with AI assistance and reviewed by our editorial team.
Status check: what is confirmed on 7 November 2026
Sources for the table: Yotta's release and press list, the CEO interviews, NVIDIA's newsroom and SEBI's filing list.
| Claim | Source | Status |
|---|---|---|
| In the process of ordering 50,000 Vera Rubin and 45,000 GB300 GPUs; Rubin for the 120 MW D4 site | CEO interview, late August 2026 | Reported plan |
| Rubin deliveries March to June 2027, go-live May to August 2027; about $7.5 billion for Rubin hardware and networking plus $750 million for construction | Same interview | Reported plan |
| 40,000 Vera Rubin at D4 (Greater Noida, 120 MW) and 40,000 GB300 at NM2 (Navi Mumbai, 80 MW), about $12 billion over 12 months | CEO to Moneycontrol, 10 September 2026 | Reported plan, different numbers |
| A $12 billion order for 90,000 GPUs, to go out to tender | CEO to The Economic Times, September 2026 | Reported plan, third figure |
| 20,736 B300 GPUs at the 60 MW D2 site, live by August 2026; over 10,000 for IndiaAI; an NVIDIA DGX Cloud cluster worth over $1 billion | Yotta release, 18 February 2026 | Company-announced; go-live not separately announced |
| Vera Rubin ramping into full production; production shipments from autumn 2026 | NVIDIA, 31 May 2026 | Confirmed by NVIDIA |
| A Yotta or NVIDIA release on Yotta's Rubin order | None found | Not published |
| IPO in January to March 2027, up to $1.5 billion; draft papers in October | CEO to Reuters, 2 September 2026 | Reported plan; no Yotta draft on SEBI's public list |
The August wording described an order still being placed, India's largest only if completed. By contrast, AM Intelligence (AMI), set up by Greenko's promoters, announced a firm and binding order on 25 August for about 9,000 Rubin GPUs in Vera Rubin NVL72 racks for a 30 MW AI factory in Hyderabad, with delivery in the first quarter of 2027. On 6 October it added two more binding orders for 20,000 Rubin GPUs across India and Malaysia.
Why the numbers keep changing
Within about two weeks Yotta's CEO gave three different mixes. Late August: 50,000 Vera Rubin plus 45,000 GB300. On 10 September to Moneycontrol: 40,000 Vera Rubin at D4 plus 40,000 GB300 at NM2, about $12 billion over the next 12 months. Around the same time to The Economic Times: 90,000 Vera Rubin and GB300 GPUs for $12 billion, bought through a tender and delivered in batches. The August account placed D4 in Delhi; Moneycontrol places it on the Greater Noida campus, where D1 and D2 already sit.
The totals move too. Yotta's February release set a roadmap to more than 80,000 NVIDIA GPUs by FY27, and its media page carries a 30 July 2026 headline of 85,000 GPUs by the end of FY27. An 11 October headline listed on the same page still describes the $12 billion order as being planned.
Read this as a procurement still forming, shaped by NVIDIA allocation, financing and which anchor customers sign first. For a buyer the count matters less than one question: when could a contracted block of Rubin capacity be yours, and at what price?
Does 50,000 Rubin GPUs fit in 120 MW?
Power, not floor space, limits how many Rubin GPUs a building can run. NVIDIA's Vera Rubin NVL72 page sizes a 100 MW AI factory at 40,000 Rubin GPUs, assuming its DSX platform with MaxLPS power management. That is 2.5 kW of site power per GPU, or 48,000 GPUs for 120 MW. On the same basis 50,000 GPUs need 125 MW. NVIDIA's October 2026 datasheet rates one NVL72 rack at 227 kW (MaxP), 187 kW (MaxQ) or 156 kW (MaxLPS). AMI's own order gives a second benchmark: about 9,000 Rubin GPUs in 30 MW, or 300 per MW.
| Scenario | GPUs | NVL72 racks | GPU-rack load at 156 kW | At 187 kW | At 227 kW |
|---|---|---|---|---|---|
| August figure | 50,000 | 695 | 108.4 MW | 130.0 MW | 157.8 MW |
| September figure | 40,000 | 556 | 86.7 MW | 104.0 MW | 126.2 MW |
| NVIDIA density applied to 120 MW | 48,000 | 667 | 104.1 MW | 124.7 MW | 151.4 MW |
| AMI ratio applied to 120 MW | 36,000 | 500 | 78.0 MW | 93.5 MW | 113.5 MW |
Racks are rounded up to whole units of 72 GPUs, and the loads cover GPU racks only, before networking, storage and cooling. We do not know whether Yotta's 120 MW is IT load or total facility power. If it is total, a power usage effectiveness of 1.2, our assumption for a good liquid-cooled hall, leaves about 100 MW for IT.
The arithmetic points one way. The September figure of 40,000 fits a 120 MW building, comfortably at MaxLPS. The August figure of 50,000 would need deep power capping, a phased fit-out or more power than the headline. Ask Yotta which it is, because power-capped racks deliver less than peak throughput.
Timeline: from order to rentable capacity
The dates come from Yotta, NVIDIA, AMI and the interviews already cited.
| Date | Event | Source and status |
|---|---|---|
| 18 Feb 2026 | Yotta announces 20,736 B300 GPUs for D2, live by August 2026 | Yotta release |
| 31 May 2026 | Vera Rubin ramping into full production; shipments from autumn | NVIDIA release |
| August 2026 | B300 supercluster go-live target | Yotta; not separately announced |
| 25 Aug 2026 | AMI places binding order for about 9,000 Rubin GPUs in Hyderabad | AMI release |
| Late Aug 2026 | Yotta CEO describes 50,000 Rubin and 45,000 GB300 as being ordered | Interview, reported |
| 2 Sep 2026 | IPO targeted for January to March 2027 | Reuters |
| 10 Sep 2026 | D4 construction starting; 40,000 Rubin planned | Moneycontrol |
| 27 Oct 2026 | Vera Rubin NVL72 generally available on OCI | NVIDIA newsroom |
| 17 Nov 2026 | NVIDIA third-quarter results call | NVIDIA |
| Jan to Mar 2027 | IPO targeted, up to $1.5 billion | Reuters |
| Mar to Jun 2027 | Vera Rubin deliveries to D4 | Reported plan |
| May to Aug 2027 | D4 go-live | Reported plan |
| Second half of 2027 | Rubin Ultra systems due | NVIDIA roadmap |
Five risks to the date
Construction. On 10 September Gupta said D4 construction was starting. Going live by August 2027 leaves about 11 months for a 120 MW liquid-cooled hall, which is fast by any standard (our assessment, not Yotta's).
Order and financing. No signed order has been announced. Reuters reported that IPO proceeds would partly buy GPUs and that Yotta is exploring structures in which partners buy GPUs through special-purpose vehicles, share the revenue and hand over ownership after four to five years. Gupta told Moneycontrol that IPO money would mainly fund data centres and sovereign cloud, with GPUs financed through revenue-share contracts, leasing and investment vehicles. The draft IPO papers expected in October do not appear on SEBI's public list of filings, though a confidential pre-filing would not show there.
Anchor tenants first. Large blocks of the B300 cluster are already committed to NVIDIA's DGX Cloud and the IndiaAI Mission. Gupta told Reuters that global clients make up 75% to 80% of Yotta's customer base. Early Rubin capacity will probably go to large, long-term buyers before on-demand users.
Cooling. NVIDIA designs Vera Rubin NVL72 for 100% liquid cooling at a 45°C coolant inlet, so the hall has to be fully liquid-ready on day one.
The next generation. NVIDIA's roadmap puts Rubin Ultra systems in the second half of 2027, so D4 may open within months of a newer part. Our GTC 2027 buyer briefing covers that roadmap and the reported Kyber rack delay.
How Vera Rubin fits with Yotta's Blackwell supply
Most capacity Indian teams can use in the next nine months is Hopper and Blackwell. Yotta's announcements and its Shakti Cloud price list on 7 November 2026 show:
| GPU | Site | Count stated | Status on 7 Nov 2026 | How you buy it today |
|---|---|---|---|---|
| H100 SXM | Shakti Cloud | Over 10,000 GPUs of all types live (Feb 2026) | Live | 1x VM on demand at ₹356 per hour; 8x bare metal at ₹428 per GPU-hour monthly |
| B200 | Shakti Cloud | Not stated | Listed | 8x HGX B200 bare metal at ₹473 per GPU-hour on monthly to two-year terms |
| B300 | D2, Greater Noida, 60 MW | 20,736 | Listed from one-year terms | 8x HGX B300 bare metal from ₹1,056 per GPU-hour (one year) to ₹380 (five years) |
| GB300 | NM2, Navi Mumbai, 80 MW | 45,000 (Aug) or 40,000 (Sep) | Reported plan, no date | Not offered |
| Vera Rubin | D4, Greater Noida, 120 MW | 50,000 (Aug) or 40,000 (Sep) | Reported plan, go-live May to August 2027 | Not offered |
Yotta says data transfer is included in the bare-metal price and InfiniBand interconnect is charged separately. The page does not say how GST applies, so confirm tax treatment in any quote.
What does Rubin buy you over Blackwell? NVIDIA claims Vera Rubin NVL72 delivers one-tenth the cost per million tokens of GB200 NVL72 and up to 10x more tokens per megawatt, measured on Kimi-K2-Thinking with 32K input and 8K output tokens. It also claims mixture-of-experts training with one-quarter of the GPUs, for a 10-trillion-parameter model trained on 100 trillion tokens in a month. NVIDIA marks these projections as subject to change, and they compare against GB200, not the B300 or GB300 Yotta is installing, so the gap against Blackwell Ultra will be smaller. Each Rubin GPU carries 288 GB of HBM4 at 19.2 TB/s.
For rupee prices across Indian providers and the IndiaAI portal, see our IndiaAI 10,000-GPU empanelment guide.
Where IndiaAI compute fits
Yotta's February release committed more than 10,000 B300 GPUs from the D2 supercluster to the IndiaAI Mission, for foundation models, research institutions, startups and public platforms. That capacity reaches users through the IndiaAI compute portal, which has eligibility rules by user type and an approval process.
Separately, C-DAC's request for empanelment of 7 October 2026, for up to 10,000 AI compute units, covers H100, H200 and later or equivalent next-generation accelerators, with quantities and prices left to a Stage-2 procurement. Bids close on 13 November 2026. In principle an empanelled provider could offer Rubin in a later round. Nothing published says Yotta will put D4 capacity into IndiaAI, and Vera Rubin is not on the portal today.
The practical split for 2027:
- Eligible startups, researchers and government bodies should use the portal now and watch for next-generation rounds.
- Enterprises that are not eligible buy commercially. Rubin from Yotta will be a commercial contract.
What Indian GPU buyers should do now
| Your situation | What we would do | Why |
|---|---|---|
| Need GPUs before mid-2027 | Rent H100, B200 or B300 now on monthly to one-year terms | Rubin in India is not due before May to August 2027 even on Yotta's plan |
| Planning a large 2027 to 2028 training run | Ask Yotta for a written Rubin reservation with a delivery date, slip credits and a B300 or GB300 fallback | Order and construction are both still in progress |
| Serving inference at scale on Indian data | Start on Blackwell in India; benchmark Rubin when D4 opens | NVIDIA's token-cost claims are vendor projections against GB200 |
| Eligible for IndiaAI | Use the portal now; watch C-DAC Stage 2 for next-generation units | Subsidised rates beat commercial lists |
| Need Rubin in 2026 or early 2027 | Look at regions abroad, and check data residency first | No Indian Rubin capacity is live |
| Committing multi-year spend | Add substitution, price-protection and exit clauses | Rubin Ultra is due in the second half of 2027 on NVIDIA's roadmap |
Worked example: when would Rubin be worth paying more for?
No Indian Rubin price exists yet, so the useful sum is a break-even price. Take a team that needs 512 GPUs for 12 months of training.
Today's baseline on Blackwell. At Yotta's listed ₹473 per GPU-hour for 8x HGX B200 bare metal, which is also its one-year rate:
- GPU-hours: 512 × 8,760 = 4,485,120
- Cost: 4,485,120 × ₹473 = ₹2,12,14,61,760, about ₹212 crore, before GST and InfiniBand charges
The break-even rule. If a Rubin GPU finishes your job S times faster than a B200, the same job needs 1/S of the GPU-hours. Rubin is cheaper whenever its hourly price is below ₹473 × S.
| Assumed speed-up on your workload (S) | Rubin GPU-hours needed | Break-even Rubin price per GPU-hour |
|---|---|---|
| 1.5x | 2,990,080 | ₹709.50 |
| 2x | 2,242,560 | ₹946.00 |
| 3x | 1,495,040 | ₹1,419.00 |
The speed-ups are illustrative assumptions, not benchmarks. Your real S depends on model size, precision (NVFP4 versus FP8 or BF16), sequence length and how well your stack uses NVLink 6, so run your own training step on both before you sign. If Yotta quotes Rubin above ₹946 per GPU-hour, you need better than a 2x real-world gain over B200 just to break even. One reference point: Yotta's one-year B300 list price of ₹1,056 is already 2.23 times its one-year B200 rate (₹1,056 ÷ ₹473), so a B300 has to beat a B200 by more than that to win on this job.
Questions to put to Yotta, or any Indian GPU cloud, before you sign
| Topic | Question | Why it matters |
|---|---|---|
| Order status | Is the Vera Rubin order binding, and for how many GPUs? | No signed order has been announced |
| Delivery | What committed date applies to my block, and what credits apply if it slips? | Construction was only starting in September 2026 |
| Substitution | Can my reservation move to B300 or GB300 if Rubin is late? | Keeps your project on schedule |
| Power | Is quoted capacity power-capped, and what sustained throughput is guaranteed? | 50,000 GPUs strains 120 MW |
| Network | InfiniBand or Spectrum-X, and is interconnect billed separately? | Yotta bills InfiniBand separately today |
| Allocation | How much capacity is reserved for anchor tenants and IndiaAI? | Sets what is left for on-demand use |
| Residency | Do control plane, logs and backups stay in India? | DPDP and sector rules |
Data residency, DPDP and the tax angle
For Indian personal data, an India-hosted GPU removes a cross-border transfer question that a foreign region reopens. Most obligations under the DPDP Rules start 18 months after their 13 November 2025 notification, on 13 May 2027, in the same window as D4's planned go-live. Our DPDP Rules 13 May 2027 checklist covers what has to be ready.
Tax policy is also pulling foreign demand into Indian halls, and Gupta told Reuters the February tax holiday had lifted overseas customers' confidence. The 1 February 2026 Budget proposed the holiday until 2047 for foreign companies serving cloud customers globally from Indian data centres, with Indian customers served through an Indian reseller. The Taxation and Other Laws (Amendment) Act, 2026, published in the Gazette on 17 August 2026, extended it to data centres an Indian company leases and operates, not only owns. Our piece on the India cloud tax holiday to 2047 explains what finance teams should prepare.
How eCorpIT can help
eCorpIT is a Gurugram-based technology organisation, founded in 2021, assessed at CMMI Level 5 and MSME certified, with senior-led engineering teams working across AWS, Microsoft and Google platforms. Our AI and machine learning team sizes training and inference in GPU-hours, runs like-for-like benchmarks on your own models across Indian GPU clouds and hyperscalers, and reviews delivery, power and exit terms in GPU contracts. Talk to us at /contact-us/.
Last updated: 7 November 2026.